Review output yield and ingredient variance

Compare actual output to the processed target, then review each ingredient to explain the difference.

Steps

Where in KEMET: Production → Production reports → Yield and usage variances

تبويب التحضير وقائمة أوامر الإنتاج
تبويب التحضير وقائمة أوامر الإنتاجView full size
  1. Open the production report

    From the preparation register open the report and choose period, branch and item.

  2. Compare plan with actual

    Output variance = actual minus planned. Yield = actual ÷ planned.

  3. Check each ingredient

    Open ingredient variance and compare planned with issued in the same unit.

  4. Check the cost

    With permission, see batch cost and unit cost.

  5. Keep the reference

    Keep the batch number or export the report. Corrections are made on the original production order.

Fields and buttons

Field or button When to use it Result and how to check
Planned and actual outputCheck the batch date and locationPlan 30 and actual 28 yields a variance of −2 and about 93.33% yield.
Production typeCheck whether this was recipe or quick productionIngredient variance requires recipe production and recorded consumption.
Ingredient and unitCompare expected and actual usage in the same unitCompare 0.3 L against the issue in litres.
Batch costOpen the journal for a completed, posted batchOutput follows the issued ingredients and other costs evidenced on the transaction.
Batch referenceUse the reference to trace stock or investigate report differencesReconcile the report with prepared-lot balance and movements after production.

Screen images

Worked example

A target of 30 yields 27

Output variance is minus three and yield is 90%. If the planned issue was 20 kg and actual issue was 21 kg, ingredient variance is plus 1 kg. Investigate the two measures separately.

From ChatGPT or Claude

Once KEMET is connected to your assistant, copy and send this request:

Show production yield and ingredient variance for this week's orders.

The assistant reads data right away. Any change is shown to you in KEMET for approval before it runs, within your account permissions only.

Tools the assistant uses here
  • restaurant_report_production_output_variance
  • restaurant_get_production_order_execution_times
  • restaurant_get_production_batch_materials

How to connect the assistant to KEMET

Verify the result

  • Comparison uses one batch, branch and unit.
  • The cost basis is visible, and the explanation has an identifiable record where available.

Common problems

Yield is blank

Quick production without a recipe reports output and leaves recipe yield and variance blank.

Cost is hidden or estimated

Check cost access and ingredient valuation. Open the batch document to verify the recorded cost basis.